Veligonda works on track, ₹905 crore allocated for R&R and reservoir filling: Ramanaidu

Minister says major tunnel, canal and rehabilitation works are progressing, rejects YSRCP charge of inadequate funding for the project

An additional ₹905 crore has been allocated in the State Budget towards relief and rehabilitation (R&R) compensation for displaced families and for filling the Nallamalasagar reservoir, Water Resources Minister Nimmala Ramanaidu said during an inspection of the Veligonda project works at Dornala in Markapuram district on Tuesday.Accompanied by district officials, the Minister visited the twin tunnels of the project and reviewed the ongoing tunnel lining works as well as the removal of the tunnel boring machine (TBM) from Tunnel-2.Addressing the media, Mr. Ramanaidu said the construction of the retaining wall, wing walls and return walls for the head regulators had been completed.immala Ramanaidu inspecting the tunnel lining of Veligonda project at Dornala in Markapuram district on Tuesday.

An additional ₹905 crore has been allocated in the State Budget towards relief and rehabilitation (R&R) compensation for displaced families and for filling the Nallamalasagar reservoir, Water Resources Minister Nimmala Ramanaidu said during an inspection of the Veligonda project works at Dornala in Markapuram district on Tuesday.

Accompanied by district officials, the Minister visited the twin tunnels of the project and reviewed the ongoing tunnel lining works as well as the removal of the tunnel boring machine (TBM) from Tunnel-2.

Addressing the media, Mr. Ramanaidu said the construction of the retaining wall, wing walls and return walls for the head regulators had been completed.

Advertisement

Powered by:

00:04

He said that, to enable the flow of 1 TMC of water from Kollam Vagu into the tunnels, 58,000 cubic metres of muck had been removed out of the total 1.80 lakh cubic metres accumulated in the area. In Tunnel-1, 40,000 cubic metres of muck had been cleared so far from the total 1.20 lakh cubic metres obstructing the flow of water.

The Minister said more than 5.5 km of the total 7-km lining work in Tunnel-2 had been completed during the 20 months since the coalition government assumed office. The remaining 1.5 km is expected to be completed by the end of July, he said.

Mr. Ramanaidu said the 5.3-km retaining wall for the feeder canal, the construction of which commenced in January, had been completed within five months.